淮安市2019年农村危房改造融合任务进度表(10月)

发布时间:19-11-08 字体:【  】  【关闭窗口】 来源:淮安市住房和城乡建设局

                                                                                                                                                                                                                                                                                                                   

县区省级任务(1410户)市阳光扶贫办任务(2533户)融合任务(2648户)
任务数开工竣工任务数开工竣工任务数开工竣工
开工数开工率竣工数竣工率开工数开工率竣工数竣工率开工数开工率竣工数竣工率
清江浦区33100.00%3100.00%44100.00%4100.00%44100.00%4100.00%
淮阴区35335299.72%34196.60%72071699.44%69496.39%72772399.45%70196.42%
淮安区125125100.00%125100.00%380380100.00%31983.95%390390100.00%390100.00%
洪泽区1313100.00%1292.31%1414100.00%14100.00%1616100.00%1593.75%
涟水县378378100.00%378100.00%70470399.86%70399.86%74474399.87%74399.87%
金湖县305305100.00%305100.00%413413100.00%413100.00%445445100.00%445100.00%
盱眙县233233100.00%233100.00%298298100.00%29498.66%322322100.00%31898.76%
合计1410140999.93%139799.08%2533252899.80%244196.37%2648264399.81%261698.79%
注:融合任务是省级任务与市扶贫办任务叠加形成。三项任务统计均包括结合农房改善项目完成的危房改造。开工数包括竣工数。